Sunday, February 28, 2010

Wired Roof


Electrical wiring in the roof is completed, and we are ready for inspection, closeout and blow-in insulation this week.

Wednesday, February 10, 2010

West Elevation


All windows and doors are in . . . but the glass doors on the west side have been replaced with temporary doors during construction activity.

Saturday, February 6, 2010

2x8 Roof Framing


2x8's are being used to frame over the ceiling for the exterior roof. The space between will be filled within blown insulation.

Interior Door View


Here is an interior view looking from the area of the kitchen towards the cabin side door.

Tuesday, February 2, 2010

Porch Construction


Construction of the covered wooden porch on the north side of the cabin is underway. Window and door installation will also be completed this week.