Tuesday, May 25, 2010

Shingles and Flashing


Copper flashing and shingles are finishing off the roof work this week.

Friday, May 14, 2010

Electrical


Interior framing and electrical wiring is being finished up this week at the cabin. We are also in the process of working out the details of the kitchen and bathroom cabinet and fixture designs.

Saturday, May 8, 2010

Plumbing


Rough-in plumbing has been completed for the cabin including the laundry room, bathroom and kitchen. This is a photo of the sink/toilet side of the bathroom.